Louisiana › Vermilion Parish › Starbase development timeline
Starbase Louisiana: estimated development timeline
Construction from 2027 and a first launch targeted 2029 are the only public dates. Here are the phases in between, when each is likely to land, and which trades get bought in each.
Checked 29 August 2026 · Phases are Bizer’s estimate
Two dates are public: construction from 2027, and a first launch targeted as soon as 2029. Everything between them is unannounced. This page lays out the phases a build like this runs through, roughly when each one lands, and which trades get bought in each, so you know whether your window is next year or 2030.
Read the badges. The announced dates are sourced at the bottom. The phase order and the windows are Bizer’s estimate, built from what was announced and from how coastal industrial projects of this size actually sequence. Nobody outside SpaceX has a schedule, and anyone selling you one does not have it either.
What is actually announced
Short list, because it is a short list.
| Item | Announced |
|---|---|
| Announcement | 25 August 2026, SpaceX with the State of Louisiana |
| Construction | Expected to begin in 2027 |
| First launch | Targeted as soon as 2029 |
| End state | Five launch complexes, two pads each, so ten pads |
| Also planned | Propellant farms and propellant production, power generation, vehicle processing, residential housing, deep-water shipping, an airport |
| Site | About 125,000 acres at Pecan Island, Vermilion Parish |
| Jobs | 3,000 direct over ten years, 8,100 indirect estimated |
| Reviews | Louisiana DEQ, the FAA and the Army Corps of Engineers |
Note what is missing: no phase plan, no package breakdown, no named prime contractor, no supplier portal. That is normal this early, and it is also why the timeline below is an estimate rather than a schedule.
The phases, and what each one buys
Stated by SpaceX or the State of Louisiana on 25 August 2026, and sourced at the bottom of this page.
Our read of the ordinary sequence for a coastal industrial build of this size. Not from SpaceX, and not a schedule.
Permits, surveys and the paperwork nobody photographs
Before a machine moves, the project has to clear federal wetlands review, an FAA process for a launch site, and Louisiana environmental permitting. Reporting points at the Louisiana Department of Environmental Quality, the FAA and the Army Corps of Engineers, with dockets expected to open in 2027.
This phase is quiet and it is where the schedule is really decided. It also buys real work: somebody has to survey 125,000 acres of marsh, drill it, and document what lives on it.
Access, fill and laydown
Pecan Island sits on a chenier, a shell ridge in marsh, reached by Louisiana Highway 82. Nothing heavy gets built until there is a way in, ground firm enough to carry it, and somewhere to stage it.
Expect this to be the longest and least glamorous phase, and the one with the most local content. Fill, haul roads, canal and dock access, laydown yards, and the highway work that lets an oversize load reach the site at all.
Power, water and somewhere to sleep
The announcement names power generation and residential housing for employees as part of the campus. In a parish with almost no rooms, the workforce has to be housed and fed before it can be large.
Camp infrastructure usually runs in parallel with earthwork rather than after it, which is why a catering or lodging business should not think of itself as late-cycle here.
First launch complex and vehicle processing
The announced buildout is five launch complexes with two pads each, plus propellant farms and vehicle processing. A first launch in 2029 means one complex, not ten.
This is the concrete-and-steel phase: deep foundations in soft ground, flame trench and deluge works, tower steel, and the high-spec welding that goes with cryogenic service.
Propellant production, deep water and an airport
SpaceX describes a self-sustaining spaceport: propellant production on site, deep-water shipping, and an airport. Each of those is an industrial project in its own right, and they run long after the first launch rather than before it.
Deep-water access in this location means dredging and marine construction on a scale that carries its own federal permits, which is one reason it is unlikely to gate the first flight.
First Starship launch
The announced target is a first launch as soon as 2029. Treat “as soon as” as doing real work in that sentence.
A launch does not end the buying. An operating spaceport is a permanent industrial customer: maintenance, logistics, inspection, catering, waste, security, and the ordinary services a workforce of thousands needs every day in a place that currently has none of them.
Buildout to ten pads
Five complexes with two pads each is the announced end state, and Elon Musk has separately spoken of more than a dozen towers. That is ambition rather than a documented plan, and the two are worth keeping apart.
For a supplier the useful read is that the work does not arrive as one contract in 2027. It arrives as a decade of packages, and the firms in the second decade will mostly be the ones who were already known in the first.
The two-year plan, against the only precedent
Boca Chica is the only comparison that exists, and it is worth putting the numbers side by side rather than describing them.
| Boca Chica, Texas | Pecan Island, Louisiana | |
|---|---|---|
| Site chosen | 2014 | 2026 |
| Construction began | 2015 | 2027, planned |
| First orbital launch | April 2023 | 2029, targeted |
| Construction to launch | About eight years | About two years |
That gap is the single most important thing on this page, and it cuts both ways.
Why Louisiana could genuinely be faster. Boca Chica was inventing the vehicle while building the site. Starship exists now and has flown. Louisiana is building a launch site for a known rocket, with a decade of hard-won knowledge about what a pad, a flame trench and a deluge system actually need. SpaceX also builds faster than almost anyone, and the site is enormous, which means many crews can work at once without tripping over each other.
Why two years is still very aggressive. Boca Chica is a few hundred acres on firm ground with road access. This is 125,000 acres of subsiding coastal marsh, ten miles from open water, on one highway, in hurricane country, needing federal wetlands permits over an area reporting describes as more than 200 square miles. Ground has to be made before anything can be built on it.
Our honest read: 2027 for first earthmoving is plausible if permitting goes smoothly, and a 2029 launch would be remarkable. A first launch in the early 2030s would still make this the fastest large spaceport build in American history. Neither outcome changes what a contractor should do this year.
How to tell whether it is on track, without waiting for a press release
You do not need inside information. Large projects announce themselves through public filings long before they announce themselves through announcements.
What to watch, in rough order of appearance
- Army Corps of Engineers public noticeA Section 404 wetlands permit application becomes a public notice with a comment period. That is the clearest public signal the design is real and specific.
- FAA activity for the siteA launch site involves the FAA, and its environmental and licensing steps are public. Reporting points to dockets opening in 2027.
- Louisiana DEQ permit applicationsAir and water permits for propellant production and power generation are filed with the state and are public.
- DOTD work on Louisiana Highway 82Highway and bridge lettings are published. Access has to be solved before heavy delivery, so this moves early.
- A named prime or program managerThe moment an engineering and construction firm is announced, your target changes from SpaceX to that firm’s supply chain.
- Survey and geotech crews on the groundThe least formal indicator and often the earliest. People in Vermilion Parish will see this before anyone reports it.
What this means for your business now
The timeline above has one practical use: knowing whether to move this year or watch for two.
- Survey, environmental, geotech and marine support: your window is now These are bought before groundbreaking, not after. If that is your trade, being unknown in 2027 means missing the phase you are best suited to.
- Earthwork, hauling, marine and civil: qualify this year The access and fill phase is the biggest local-content opportunity in the whole build, and vendor qualification happens before procurement, not during it.
- Steel, welding, electrical and industrial services: 2028 is not far Certifications, procedures and welder qualifications take months to put in place and are checked before award, not after.
- Camp, catering, lodging, security and services: earlier than you think A workforce has to be housed and fed while the ground is still being made. This is not a phase that waits for a launch.
- Everyone: get findable and get contract ready The supplier registry is free to be in, and being contract ready is the same paperwork that wins state and federal work whatever happens here.
One thing not to do. Do not buy equipment, sign a lease or hire against this timeline. Nothing is built, no scope has been published, and no contract has been let. Qualification is cheap and useful whatever happens. Capacity bought on the strength of a press release is neither.
Sources and dates
- Louisiana Economic Development, “SpaceX Launches New Era of Commercial Spaceflight with $100 Billion Louisiana Campus”, for the 2027 construction start, the 2029 launch target, the five complexes with two pads each, propellant production, power generation, vehicle processing, housing, and the jobs figures. Checked 29 August 2026.
- SpaceX statements reported by SpaceNews, Fox Weather and Fortune, for ten pads, deep-water shipping and an airport, and for Elon Musk’s separate remarks about more than a dozen towers. Checked 29 August 2026.
- Permitting through the Louisiana Department of Environmental Quality, the FAA and the Army Corps of Engineers, and dockets expected in 2027: NASASpaceflight and Louisiana Radio Network reporting, 27 August 2026.
- Boca Chica comparison: site selected 2014, construction from 2015, first orbital Starship flight 20 April 2023. Public record.
- Phase order, windows and the trades in each phase are Bizer’s estimate, not SpaceX’s plan.
Wondering where your trade lands in this?
Tell Miles what your business does and he will walk you through which phase buys it and what has to be in place first. Free to talk, any hour.
Free, no account needed. Answered by Miles, Bizer’s Louisiana business AI agent.
